Project Map and Timetable

This map shows the import route from western Ukraine via Poland to Austria and Germany.

Map of Europe showing H2 and gas pipelines

Timetable

H2EU+ Store Schedule
  • Stage 1 (2032): Realization of 60,000 t/a H2
  • Stage 2 (2033 - 2040): Increase to 500,000 t/a H2 by 2040
  • Stage 3 (2041 - 2050): Increase to 1 Mio. t/a H2 by 2050

The project is structured in three phases and is timed to match with the development of new photovoltaic, wind and electrolysis capacity in Ukraine and the conversion of transport infrastructure and storage facilities in Central Europe. A first project for the production of ~ 9,000 t/a H2 is currently being prepared for phase 1.